Replacement continues

Replacement continues

Contractors working on East Gippsland Shire Council’s Lakes Entrance seawall replacement project have en- countered some unexpected obstructions in recent weeks that slowed progress.

However, council says every endeavour is being made to still have the works completed as soon as possible, but the need to remove large chunks of concrete (the result of decades of interim repairs to the seawall) had slowed progress.

The existing 216-metre blue- stone seawall between the Lakes Entrance Coast Guard building and the existing board- walk east of the beach is being replaced with precast concrete panels, a boardwalk, platform and ramp to the beach.

The Bank Jetty carpark is closed for the duration of the project.

PICTURED: Contractors lift new concrete retaining walls into place on the Lakes Entrance seawalls project after having removed large chunks of concrete as part of the old wall.


Print  

Lakes Post

505 Esplanade
PO Box 303
Lakes Entrance, VIC 3909

P: (03) 5155 1514
F: (03) 5155 1116

Publication Day: Wednesday
Circulation: 3,531

Yeates Media

Cnr Macleod & Bailey Streets
PO Box 465
Bairnsdale, VIC 3875

P: (03) 5150 2300
F: (03) 5152 6257